How to construct Storm/Rain Water Drainage system



HOW TO CONSTRUCT STORM WATER SYSTEM
                                                


INTRODUCTION
A storm water system is a system to manage runoff from rainfall and maintain the underground water table.

OBJECTIVE:
Main objective of this method statement is to complete the work in a uniform way across all projects with accuracy and efficiency.

 MATERIAL
Bricks, Coarse Sand, Cement, Aggregate, RCC Covers, Reinforcement steel, PVC slotted pipe, Gravels, MS Rungs, MS Grating etc.

 APPARATUS / EQUIPMENT
JCB / Excavator, Tractor with Trolley/Tippers, Plate Compactor, Double Drum Roller, Mixture Machine, Auto Level, Mason Thread, Rope, Measuring tape, Plumb bob, karni, Basuli, Boring machine, Water tanker.

 HEALTH AND SAFETY PROVISION
·         Permission from the engineer in charge shall be taken before any excavation commences, and all persons involved in the task shall be fully briefed.
·         Fencing and safety signage to be put near excavated area and maintained during the progress of construction work.
·         Suitable access to be provided to trenches and pits.
·         Dewatering system is to be implemented wherever required.

PREPARATORY WORK
·         Obtain relevant approved GFC drawings.
·         All required area to be cleared for excavation. 
·         Layout work of the Storm water drainage and location of Recharge well shall be marked.
·         Bench mark should be marked over a column in nearby block.
·         NGL shall be recorded to finalize excavated quantity.

 PROCEDURE OR METHODOLOGY
·         The center line of drain and reference line is marked before start of excavation.
·         Locate the position of the Rain water harvesting well and de-silting chambers on the ground as shown in GFC drawing.
·         Excavation — Trench shall be excavated manually or with the help of JCB to the required dimensions, alignment and gradient. The excavation of trench shall commence from the starting end.
·         The bottom of the trench shall be compacted with the help of plate compactor to achieve plain and well rammed surface.
·         Bedding— 75 mm thick PCC 1:4:8 shall be laid at required level, under the brick walls of drain. The width of PCC would be thickness of brick wall +35 mm projection on both sides.
·         Brick Work —Layout for 230 mm thick or more brick work as specified in drawing is to be done over PCC. Brick work shall be started after minimum 8 hours of PCC with 1: 6 CM over PCC up to required height, keeping allowance for drain cover. Brick work shall be allowed to cure for 7 days, backfilling can be done after 3 days of curing.
·         Backfilling— Backfilling shall be done manually and compacted.
·         Installation of Drain Covers— Perforated precast RCC drain cover shall be fixed in line and level over concrete bed. Concrete bed thickness as per drawing.
·         Cleaning Up—All construction materials, tools and temporary structures shall be removed from the trenches before installation of drain cover.
·         Drain cover – Precast openable perforated drain covers should be placed.
·         Baffle wall – Half brick work baffle wall to be provided @ 15mtr c/c up to 6” below the bottom of drain cover.
·         No plaster shall be done inside the drain.





Installation of Rain Water Harvesting Well:
·         Location of Bore well shall be finalized.
·         Drilling shall be done upto a depth of approx 5 mtr above the water table or as per drawing.
·         Space around slotted pipe in the bore hole is to be filled with 10 mm stone chips. Slot size in the pipe should be 2mm wide & 100 mm in length. Slot has to provide 500mm from filter media and 1m above the last level of bore well.
·         The lower and upper ends of the pipe shall be plugged.
·         Excavation shall be done as per the size and depth of the recharge pit.
·         PCC and Brickwork shall be done as specified in the drawing.
·         Beds of Boulders, Gravels and Coarse Sand shall be laid as specified in the drawing.
·         Rungs shall be provided as per the requirement.
·         Connection to RWH well—Drains shall be connected to collection/sedimentation chamber. MS Grating to be provided at connection point to avoid any foreign material in RWH pit.
·         End plug/Cap to be provided at inlet of RWH for first rain, so that foreign material does not enter into the pit as per drawing attached.
·         Slab shall be casted at the specified height and manhole covers shall be provided as per the drawing.
·         Cleaning Up— All construction materials, tools and other unwanted shall be removed from the pit before commissioning
 INSPECTION
·         Slotted pipe and accessories should be inspected for defects and cleanliness prior to lowering. Any defective, damaged or unsound material should be repaired or replaced.
·         The prepared trench bed shall be inspected with reference to design. Uniform gradient, alignment and proper compaction shall be ensured.
·         The top level of brick work shall be checked for uniform line and level.
·         Drain covers shall not be damaged from the edges.
 

Comments

Popular posts from this blog

How to check quality of Clay or Red Bricks at site

New Education Policy of India 2022 : राष्ट्रीय शिक्षा निति योजना से छात्रों को होगा लाभ, जानें कैसे

What Is the difference between Pre-tension & Post-tension