METHOD STATEMENT FOR RAILING FIXING
METHOD
STATEMENT FOR RAILING FIXING
INTRODUCTION
The scope of this method statement is to define
the procedure that will be followed for Railing fixing.
OBJECT
· Approved
Railing Drawings.
· Detailed
section of railing.(Balcony/Stair)
MATERIAL
Stair/balcony
Railing, welding rod, Plumb bob, Measuring tape, MS plate
of 100x50 mm for stair railing , mason thread,
anchor fastener (100X8mm), Welding machine, Hammer drill Machine, Safety
Shield, Grinder, hammer.
HEALTH
AND SAFTEY PROVISION
1. The
work place is to be free from all kind of debris.
2. To
check electrical socket for work.
3. Any
kind of cable/wire is to be covered with flexible pipe and no naked wire is to
be seen.
4. Use
welding glass during welding.
PROCEDURE
Stair railing fixing
1.
If the tread is of 300mm, after 100mm from the starting of
tread MS plate of 100X50 is to be fixed by anchor fastener of 100 X 8 as shown
in the drawing.
2.
Stair railing to be fixed with adjacent sides in plumb.
3.
After checking the plumb and line, weld the stair railing to
the pre-fix MS plate.
4.
End
point of first flight and start point of second flight at landing/floor should
be at the same level.
5.
Uniform
gap should be maintained between finished floor and railing.
6.
Height
of railing should be uniform throughout.
7.
Welding
joints should be neatly grinded.
8.
Anchor
fastener should be tightly fixed.
Balcony railing fixing
1.
As per our standard, skirting top will be 100mm from top of
tile and balcony railing top will be 950 mm for low rise and 1050 mm for high
rise, from finished floor level.
2.
Railing top level should be marked.
3.
Anchor fastener to be fixed at the ends of railing, in
concrete members.
4.
Holdfast to be fixed at bottom of railing.
5.
75 X 75 mm coping of concrete (1:2:4) to be done all around
at the bottom to fix the holdfast.
6.
Level and verticality of railing to be checked while fixing
the railing.
INSPECTION
1.
Railing height and design must be as per drawing/standards.
2.
Railing must be in line and level.
3.
Railing must be in plumb and right angle.
4.
Vertical members of stair railing must be welded on the
middle of the prefixed MS Plate at
bottom.
5.
All welding joints must be finished smoothly by grinding.
6.
One coat of red oxide primer should be coated on the railing
before fixing.
7.
All welded parts needs to be applied with primer again immediately
after completion of welding.
8.
Anchor Fastener should not be loose.
Comments